Roadwork in Bingen October 2-4, 2023

Overlay north Cedar, Franklin between Pine and Cedar, Chip Seal and Fog Seal of Pine and Vine
Map highlighting streets where roadwork will happen
Fall 2023 Roadwork Map

Teams from Klickitat County Public Works will be in Bingen the week of September 25, 2023 to complete several projects under Bingen's Transportation Improvement Board (TIB) grant.  

Projects, locations, and updated timing are as follows:

  • Overlay northernmost block of Cedar - *completed* Thursday, September 28
  • Overlay Franklin beginning at Pine and ending at Cedar - Thursday, September 28
  • Chip seal and fog seal Pine and Vine - Monday, Tuesday, and Wednesday, October 2, 3, 4

Impacted homes will receive a tag on their front door. Please follow all instructions to remove parked cars.  Please call City Hall at 509-493-2122 x1 with questions.